A solar trailer for a wireless network site is a towable power platform that keeps telecom equipment running where the grid is absent, unreliable or too expensive to extend. It is not the same product as a solar light tower, and it is not the same as a solar surveillance trailer — the load profile is different, and that difference decides the array size, the battery bank and the price.
This guide sets out how to specify one: what the trailer has to power, how to size solar and storage for the worst month rather than the best one, when a diesel genset still earns its place, and what to put in the request for quotation so suppliers quote the same thing.
1. Start With the Load, Not the Panel
Telecom loads run continuously. A light tower draws power for 10 to 12 hours a night; a radio site draws power 24 hours a day, all year, and often must keep running through a mains outage. That single difference multiplies the energy requirement by two to three times for the same nominal wattage.
List every device and its real consumption before discussing equipment:
| Equipment | Typical draw | Duty cycle |
|---|---|---|
| 4G / 5G remote radio unit, per sector | 200 – 600 W | 24 h, varies with traffic |
| Microwave or point-to-point link | 30 – 80 W | 24 h constant |
| Small cell or repeater | 100 – 300 W | 24 h constant |
| Router, switch, NMS | 20 – 50 W | 24 h constant |
| CCTV and site lighting | 30 – 100 W | 24 h or night only |
A 300 W continuous site needs 7.2 kWh a day before losses. Add 15 percent for inverter and cabling losses and the design target becomes roughly 8.3 kWh a day — the number that sizes everything else.
2. Size for the Worst Month, Not the Annual Average
Most undersized solar trailers are not undersized on paper; they are sized on a good month. A system designed against annual average irradiance will fail every winter, and at a telecom site a failure means a dropped cell, not a dark car park.
Use the worst-month daily sun hours for the actual destination and derate for heat, dust and panel soiling:
- Coastal Peru and Atacama edges: 2.5 – 3.5 peak sun hours in the dullest month
- Andean highlands: 4.5 – 5.5, but cold reduces usable battery capacity
- Gulf and Saudi interior: 5.0 – 6.0, with derating for 45 °C plus ambient
- West and East African savannah: 4.0 – 4.8, with a pronounced rainy season
- Northern Europe: 1.2 – 2.0 in December, which usually rules out solar-only
Array size in kWp = daily kWh ÷ (worst-month sun hours × 0.75). For the 8.3 kWh example at 3.0 sun hours, that is roughly 3.7 kWp. In a 1.5-hour location the same site needs 7.4 kWp, which is usually the point where a hybrid with a genset becomes the cheaper answer.
3. Autonomy: How Many Days Without Sun
For a network site, autonomy is a service-level decision, not a preference. Three to five days without solar input is the common range for remote sites where a technician cannot reach the trailer quickly; two days is normal where maintenance is easy.
Battery kWh = daily kWh × autonomy days ÷ usable depth of discharge. With LiFePO4 at 80 percent usable, the 8.3 kWh site needs about 10.4 kWh per day of autonomy — 31 kWh for three days. Lead-acid at 50 percent usable needs 16.6 kWh per day of autonomy, which is why lead-acid trailers end up heavy and expensive at this load level.
Two further points matter in the field:
- Cold charging. LiFePO4 must not be charged below 0 °C. Sites that see frost need heated battery compartments or a charge-inhibit setting, not just a bigger bank.
- Heat. Sustained 45 °C ambient shortens battery life and derates output. Ventilated, shaded enclosures are worth more than an extra panel.
4. When a Diesel Genset Still Belongs on the Trailer
Solar-only is the right answer when the worst-month sun is workable and the site can tolerate a short autonomy window. A hybrid trailer with an auto-start genset makes sense when:
- The site is above roughly 50° latitude, or in a monsoon belt with weeks of low yield
- Load will grow — adding a second operator or a 5G upgrade after commissioning
- Fuel delivery is easier than battery replacement, and the site is secure enough to store fuel
- The customer’s SLA requires guaranteed uptime regardless of weather
A correctly sized hybrid runs the genset a small fraction of the year, using it as a charger rather than a prime power source. The controller should start on state of charge and stop at an upper limit, so the site runs unattended. Budget for the fuel that gets consumed while the genset is idle too — diesel does not improve with age.
5. Security, Transport and Site Access
A trailer full of battery is a theft target. Specify lockable battery compartments with concealed hinges, a GPS tracker, a door-tamper alarm reported to the same monitoring platform as the power data, and where local conditions require it, mechanical anchoring points for chaining to a concrete pad.
Transport constraints are decided by the last kilometre, not the highway. Confirm the access road width, gate opening, turning circle, towing vehicle and whether the trailer will be lifted by crane or forklift. A dual-axle trailer with a heavy bank is stable on road but awkward on a mine bench; a single-axle platform is easier to position but limits battery capacity.
Two engineering details that get skipped and later cause failures:
- Lightning and surge. A mast-mounted antenna or panel array on an exposed site needs earthed structure, surge protection on the DC and AC sides, and a separate earth electrode from the equipment cabinet.
- Wind rating. Deployed panels and any mast must be rated for the local gust, not the average wind speed. Ask for the rated figure in writing, with the panels stowed and deployed.
6. Remote Monitoring: Decide What the NOC Needs to See
At a telecom site the trailer is part of the network, so it should report like one. Minimum useful data set: state of charge, PV yield today, load current, genset run hours, cabinet temperature, door status and alarm state. If the operator runs an SNMP or Modbus platform, confirm the protocol and register map before manufacture rather than after delivery.
Remote access needs its own connectivity path. If the site exists to provide coverage, the trailer’s own 4G link may be the only backhaul available — check coverage at the exact position, not at the nearest town.
7. What to Put in the RFQ
Suppliers can only quote comparable numbers if the requirement is written the same way. Include:
- Equipment list with measured or nameplate consumption, and duty cycle for each item
- Required autonomy in days, and whether that is at full load or average load
- Destination and worst-month sun hours, or the site coordinates
- Ambient temperature range, dust, humidity and altitude
- Whether a genset is acceptable, optional, or excluded
- Battery chemistry preference and any transport restrictions (lithium is a dangerous-goods shipment)
- Towing vehicle, access constraints and expected number of relocations per year
- Monitoring protocol and who owns the SIM and data plan
- Certification, marking and documentation required for import
- Spare parts and service interval expectations
Our solar trailer platform is built for remote sites without grid power; the same sizing method is used when the payload is communications equipment rather than cameras. For a power-only requirement, see the LF2971 mobile energy trailer. If you are still defining the site, the remote-site selection guide walks through the same load-first logic.
For emergency response, where the trailer must deploy in minutes and link with other units, see our Rescue Flagship concept for last-mile disaster relief.
Turn the Site Load Into a Sized Configuration
Send the equipment list, destination and autonomy requirement, and we will return an array size, battery capacity and whether a genset is needed — with the assumptions shown, so you can check them.